Inaccurate Representations Can Lead to Differing Site Conditions Claim
May 26, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn the
prior posting, I discussed a case dealing with a differing site condition. In that case, the owner did not have an affirmative duty to make a representation and there was no inaccurate representation made by the owner that misled the contractor.
Well, what about when there is an inaccurate misrepresentation regarding the site? This was the circumstance in an older Florida case where a dredging contractor had a successful differing site conditions claim. See Jacksonville Port Authority v. Parkhill-Goodloe, Co., Inc., 362 So.2d 1009 (Fla. 1st DCA 1978).
The government provided inaccurate information as to the lack of rock that would be encountered during the dredging that was relied on by the dredging contractor. But the government had “
superior knowledge” that there was rock in an adjacent location based on a prior claim from a contractor, yet the government did not disclose the possibility that rock could be encountered.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Data Center Construction: Contractors Must Step Up
May 26, 2026 —
Aarni Heiskanen - AEC BusinessI attended the
Datacenter Forum 2026 in Helsinki last week. Over 400 people packed the room. Walking out, I had one overriding thought: Is construction operating in a different century from the technology it is being asked to house?
Is Our Industry on Par?
Ciarán Forde, Senior Vice President at CTS Nordics, opened the forum with a statement that set the tone for everything that followed: data centers are no longer just a technical challenge; they are a national strategy. Before AI, Ciarán had worked in telecoms, where data centers were already complex. But now, he said flatly, everything has changed, and the industry must rethink everything.
The numbers behind the claim are staggering. Current AI data center racks run at 40 to 100 kW. In three years, 800 kW per rack is on the roadmap. And the development cycle for a new chip is roughly one year, which means deployments begin aging out almost as soon as they are commissioned.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
It’s More Than a Feeling: Proving Construction Damages and When You Should Hire an Expert to Help Do It
July 27, 2026 —
Bradley E. Sands & Katie McCracken - ConsensusDocsWhen you win a bid, you might be singing that everything is going your way. Then something goes wrong. The owner hands you defective plans, sits on RFI responses or other critical information, or otherwise upends the work. The costs pile up through no fault of your own. You feel wronged, and you want to be made whole. But a feeling that you got burned is not enough. To recover, that feeling has to become something the law recognizes as damages. So, what are damages, and how do you prove them?
At bottom, contract damages are the money that puts the non-breaching party (i.e., the party that doesn’t breach the contract) in the position it would have occupied had the contract been performed.
Reprinted courtesy of
Bradley E. Sands, Jones Walker LLP and Katie McCracken, Summer Associate, University of Georgia School of Law
Read the full story...Mr. Sands may be contacted at
bsands@joneswalker.com
'Drywall Isn't Light': Peter Lupo on Safety Management at Standard Drywall
May 26, 2026 —
Elaine Silver - Engineering News-RecordPeter Lupo has been safety director since 2019 at San Diego-based Standard Drywall Inc., a major wall and ceiling contractor. He draws on over two decades of safety experience across a wide range of commercial construction work, having previously served as safety director for general contractor T.B. Penick & Sons. He has also previously operated Peter Lupo Consulting, where he reviewed legal cases and provided expert testimony, and blogged on safety for ENR.com. Lupo recently spoke to ENR Correspondent Elaine Silver about the weight of drywall, heat hazard control, bilingual crews and how he supports safety creativity and learning on the Standard Drywall staff. The conversation has been edited.
Read the full story...Reprinted courtesy of
Elaine Silver, Engineering News-RecordENR may be contacted at
enr@enr.com
Brenda Radmacher Authors Chapter in ABA Publication on Construction Delays
May 26, 2026 —
Brenda Radmacher - The Construction SeytBrenda Radmacher, a partner in Seyfarth’s Construction Law practice and a mediator and arbitrator serving on the American Arbitration Association’s panels, is among the contributing authors to the American Bar Association’s forthcoming guide on construction disputes: Time – The Legal Implications of Project Delay in Construction.
Drawing on three decades of experience, Radmacher authors Chapter 8, Contractor Delay Damages, offering practical insight into one of the most contested issues in construction litigation and arbitration.
Read the full story...Reprinted courtesy of
Brenda Radmacher, Seyfarth Shaw LLP
Jenny Michel Named Top Lawyer by Acadiana Profile Magazine
June 29, 2026 —
Lewis BrisboisLafayette Managing Partner Jenny Michel has been named to Acadiana Profile magazine’s 2026 Top Lawyers list for Insurance Law. The annual list honors excellence across several practice areas.
To select attorneys for its Top Lawyers list, Acadiana Profile works with a research firm that conducts a peer-review survey of attorneys in the Acadiana, Louisiana region. The attorneys nominate fellow professionals who they consider the best in their field of practice.
Ms. Michel is co-chair of the London Market Group, the Pollution Legal Liability/Environmental Impairment Liability (PLL/EIL) practice, and the Energy, Marine & Power practice. She has worked with London insurers her entire career. Licensed in both Louisiana and Texas, she leads a team of experienced attorneys focused on marine, both traditional and alternate energy, onshore and offshore property, trucking and environmental insurance coverage and bad faith claims, excess monitoring, advice and litigation, both at the trial and appellate levels.
Read the full story...Reprinted courtesy of
Lewis Brisbois
New York Construction Employers Face New Reporting and Cancellation Pay Requirements Beginning December 8, 2026
October 26, 2026 —
Bradley J. Bartolomeo & Clare M. Cunningham - Lewis BrisboisEffective December 8, 2026, pursuant to the New York Construction Reporting Pay Act, employers in the New York State construction industry will be subjected to new reporting requirements and will be required to pay both union and non-union workers for certain last-minute schedule changes, even when the disruption is caused by weather, failed inspections, material shortages, site-access restrictions, or delays attributable to owners, general contractors, or other trades.
For many contractors, routine decisions that have historically been considered part of construction scheduling risk may now create mandatory wage obligations, prevailing wage compliance concerns, and potential wage-and-hour litigation exposure.
Reprinted courtesy of
Bradley J. Bartolomeo, Lewis Brisbois and
Clare M. Cunningham, Lewis Brisbois
Mr. Bartolomeo may be contacted at Bradley.Bartolomeo@lewisbrisbois.com
Ms. Cunningham may be contacted at Clare.Cunningham@lewisbrisbois.com
Read the full story...
Suit Against Broker Untimely Filed
November 09, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe insured’s suit against the broker alleging insufficient coverage was dismissed as untimely. Elite Rental Properties, LLC, et al. v. Nautilus Ins. Co., et al., 2026 La. App. LEXIS 1704 (Aug. 26, 2026).
Elite retained Southern General Agency (SGA) and The Lincoln Agency, LLC to procure insurance coverage for multiple properties. SGA/Lincoln obtained a property insurance policy from Nautilus. The property had two structures, a single-family home and a rear structure, which contained a small apartment. Elite claimed that it understood the policy to cover both structures. On September 9, 2022, a fire caused catastrophic damage to the rear structure and exterior damage to the primary structure. Nautilus denied payment for the rear structure, claiming it was not covered in the policy.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com