Nationwide Preliminary Injunction Ordering Department of Defense to Resume Review of Wind Energy Projects
September 21, 2026 —
Victor J. Roehm III, Christopher P. Colyer & Sara M. Ajeti - Snell & WilmerOn August 6, 2026, the U.S. District Court for the District of Oregon granted a preliminary injunction in Renewable Northwest v. Hegseth, Case No. 3:26-cv-01092-IM, ordering the Department of Defense (DoD) to resume processing wind energy project applications under the existing statutory and regulatory framework and staying DoD’s review freeze pending final adjudication on the merits.
Background
In 2011, Congress created the Military Aviation and Installation Assurance Siting Clearinghouse (Clearinghouse) within DoD to review wind energy projects that might affect military operations. When a wind project developer files an application with the Federal Aviation Administration (FAA), the FAA refers it to DoD to determine whether the project poses an “unacceptable risk to the national security.”
Reprinted courtesy of
Victor J. Roehm III, Snell & Wilmer,
Christopher P. Colyer, Snell & Wilmer and
Sara M. Ajeti, Snell & Wilmer
Mr. Roehm may be contacted at vroehm@swlaw.com
Mr. Colyer may be contacted at ccolyer@swlaw.com
Ms. Ajeti may be contacted at sajeti@swlaw.com
Read the full story...
Understanding the EPA’s Latest Proposed Drinking Water Contaminant Monitoring Rule, Published in Law360
September 01, 2026 —
Gordon Rees Scully MansukhaniThe U.S. Environmental Protection Agency’s (EPA) proposed Sixth Unregulated Contaminant Monitoring Rule (UCMR 6) represents another step in the federal government’s ongoing effort to identify and evaluate emerging contaminants in drinking water. The proposal would require certain public water systems to monitor and report on 30 unregulated drinking water contaminants from 2028 through 2030, while generating occurrence data that could inform future regulation and affect environmental, commercial, litigation and risk assessments.
In an article published by Law360, Gordon Rees Scully Mansukhani Senior Counsel, Ayodeji Ayolola, analyzes the scope and practical implications of UCMR 6, including the contaminants selected, the proposed monitoring requirements for public water systems, and the EPA’s continued focus on PFAS and related organofluorine compounds. The article also touches upon the potential significance of publicly available monitoring data for businesses and property stakeholders.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Arizona Court of Appeals Clarifies Homeowners Association Open Meeting Requirements
June 29, 2026 —
Jill Casson Owen, Benjamin J. Hawkins & Stephen Wright - Snell & WilmerA Z N H Revocable Trust v. Sunland Springs Village Homeowners Association, No. 1 CA-CV 25-0424 (Ariz. Ct. App. Apr. 28, 2026)
OVERVIEW
The Arizona Court of Appeals issued an opinion clarifying how homeowners associations must conduct meetings under A.R.S. § 33-1804. The decision reinforces the legislative policy favoring transparency in association governance, bringing association meeting requirements more in line with the open meeting standards applicable to public bodies under A.R.S. § 38-431 et seq. (Arizona’s Open Meeting Law).
KEY HOLDINGS
1. All Voting and Formal Actions Must Occur in Open Meetings
The Court affirmed that association boards cannot vote or take formal action during closed (executive) sessions. Under A.R.S. § 33-1804(A), associations may close portions of meetings only for “consideration” of certain enumerated topics, such as legal advice, pending litigation, or personal/financial information about individual members. The Court interpreted “consideration” to mean discussion and deliberation, not voting. The Court noted that dictionaries define “consider” as “spending time thinking about a possibility” and “formulating an opinion,” which are processes that precede formal action. This interpretation mirrors how Arizona’s Open Meeting Law (A.R.S. § 38-431.03(D)) prohibits public bodies from voting in executive session.
Reprinted courtesy of
Jill Casson Owen, Snell & Wilmer,
Benjamin J. Hawkins, Snell & Wilmer and
Stephen Wright, Snell & Wilmer
Ms. Owen may be contacted at jowen@swlaw.com
Mr. Hawkins may be contacted at bhawkins@swlaw.com
Mr. Wright may be contacted at swright@swlaw.com
Read the full story...
Doctrine of Substantial Performance When It Comes to Payment
July 27, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent non-construction case touches upon the doctrine of substantial performance when it comes to payment. In this case, a club was to make two payments to secure a rapper’s attendance. The first payment was made. The second payment was made but was a few hundred dollars short of the agreed amount. The rapper did not show up. The club claimed it substantially performed its obligations. At first glance, the argument makes sense because the second payment fell only a few hundred dollars short. But that wasn’t the case when it comes to pre-commencement payment obligations:
Substantial performance applies only when the variance from the contract terms “is inadvertent or unintentional and unimportant so that the work actually performed is substantially what was called for in the contract.” However, when one party agrees to pay the other on or before a specific date, time is of the essence, and the payor is required to pay the payee on or before that date. “There is almost always no such thing as ‘substantial performance’ of payment between commercial parties when the duty is simply the general one to pay. Payment is either made in the amount and on the date due, or it is not.”
Big Gate Records, LLC v. Washington, 51 Fla.L.Weekly D1281a (Fla. 2nd DCA 2026) (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
“The Superintendent Told Us to Do It:” Why Verbal Approval May Not Be Enough
June 02, 2026 —
Andrew Lintner - Colorado Construction Litigation BlogIn construction defect litigation, one scenario appears repeatedly: a subcontractor installs work in a manner that differs from the plans, specifications, manufacturer instructions, or industry standards after being verbally directed to do so by the general contractor, superintendent, architect, or owner’s representative.
At the time, the decision may seem minor. The project is moving quickly, the field team wants to maintain progress, and nobody wants to stop working over what appears to be a small issue. The subcontractor may trust the superintendent or project manager and assume the conversation will be remembered later if questions arise.
Years later, however, when the project experiences problems, the people involved may deny the conversation occurred, remember it differently, or simply no longer remember the project. Without written documentation, the subcontractor can find itself defending claims for defective work, even though it performed the installation exactly as directed.
Read the full story...Reprinted courtesy of
Andrew Lintner, Higgins, Hopkins, McLain & Roswell, LLCMr. Lintner may be contacted at
alintner@hhmrlaw.com
From Dark Data to Building Intelligence
July 13, 2026 —
Aarni Heiskanen - AEC BusinessIn this episode, I talk with Mark Sorsa-Leslie, founder and CEO of
Auttaa AI, whose team just won first place in Luotea’s inaugural hackathon in Helsinki for turning property maintenance from reactive firefighting into proactive forecasting with AI. Mark is a chartered surveyor with 30 years of real estate data experience, previously the founder of the UK sensor company Beringar.
We discuss why so much building data stays dark and siloed, from outdated networking technology to the shortage of people who understand both engineering and property. Mark explains how Auttaa bridges real-time building data with large language models, using what he calls an “influence graph” to surface correlations and causation across previously disconnected systems, such as linking occupancy patterns to CO2 readings to diagnose ventilation problems in minutes rather than days.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Real Estate & Construction News Roundup (8/19/26) – Single-Family Housing Investors Worry, Confidence in Multifamily REITs and Construction Backlog Falls
September 08, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, U.S. Chamber of Commerce creates Housing Advisory Council, a legal battle develops over new federal rules related to mortgage escrow accounts, hospitality dealmakers pursue ‘bigger, higher-conviction’ M&A, and more!
- In the wake of the 21st Century ROAD to Housing Act becoming law, the U.S. Chamber of Commerce has created a Housing Advisory Council with the goal of advancing market-driven policies that help increase housing supply and promote affordability. (Julie Strupp, Multifamily Dive)
- Investors in the single-family housing market are increasingly concerned about interest rates, rising insurance and home costs, and the ongoing war with Iran. (Diana Olick, CNBC)
- A legal battle is brewing over new federal rules related to accounts that hold money to pay homeowners’ property taxes and insurance payments. (Sarah Agostino, CNBC)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
The Most Expensive Signature to Not Get: Why Change Orders Matter
August 16, 2026 —
Kathryne E. Baldwin - Wilke FleuryGeorge Bernard Shaw has a quote we use a lot in my family: “The single biggest problem in communication is the illusion that it has taken place.” This is pertinent to contractors and homeowners alike because the cost of failing to get proper signatures on documents like construction contracts, and particularly, change orders, is heavy. Both contractors and homeowners are in the same boat as far as wanting to complete a job as swiftly as possible: contractors go on to their next job and homeowners can return to peace in their home. This is prime territory for either party to suggest the work be completed today and the contract or change order executed tomorrow, or even later. However, without a contract, there is no memorialization of the communication between the parties, which can lead to confusion and missed expectations on both sides.
Construction plans are rarely as neat and tidy as they originally seem to be. A contractor may uncover unforeseen conditions, an owner may request additional work or changes that require additional work, or weather interferes with project schedules or the work itself. Unfortunately, the signature that never gets collected can become one of the most expensive omissions on a project – for both sides.
Read the full story...Reprinted courtesy of
Kathryne E. Baldwin, Wilke FleuryMs. Baldwin may be contacted at
kbaldwin@wilkefleury.com