Tariffs As Taxes — What Learning Resources, Inc. v. Trump Means for Contractors and the WSDOT Specifications
March 17, 2026 —
Brett M. Hill - Ahlers Cressman & Sleight PLLCIn October 2025, we explored a pressing question for public works contractors:
should post-contract award tariffs be reimbursable? The crux of that analysis was whether tariffs imposed after contract award constitute a tax under the Washington State Department of Transportation (WSDOT) Standard Specifications, triggering reimbursement under Section 1-07.1(5)B (“tax changes”).
Since then, a landmark Supreme Court ruling in Learning Resources, Inc. v. Trump has clarified the legal nature of tariffs in a way that could significantly affect this debate.
In Learning Resources, Inc. v. Trump, 607 U.S. (2026), the U.S. Supreme Court addressed whether the President had the authority under the International Emergency Economic Powers Act (IEEPA) to unilaterally impose broad tariffs on imports.
Read the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
White and Williams LLP Ranked in the Chambers USA 2026 Guide
June 15, 2026 —
White and Williams LLPWhite and Williams LLP is proud to celebrate the Chambers USA 2026 Guide which has ranked several of the Firm's attorneys and practice groups, underscoring the Firm's overall commitment to providing client service excellence.
The Chambers USA 2026 Guide recognized attorneys Tim Davis, Managing Partner, and Nancy Frantz, Chair of the Real Estate Group, for Real Estate: Finance in the state of Pennsylvania. Randy Maniloff, Partner, Patricia Santelle, Chair Emeritus/Former Managing Partner, and Robert Walsh, Partner were ranked for Insurance in Pennsylvania, and Thomas Pinney, Partner, was ranked in Pennsylvania for Bankruptcy/Restructuring. In the state of Maryland, Partners David Gilliss and Eric Korphage were recognized for their work in Construction.
Read the full story...Reprinted courtesy of
White and Williams LLP
Trend Continues Where Unlicensed Contractors Have No Recourse
July 13, 2026 —
David Adelstein - Florida Construction Legal UpdatesThere’s been a recent trend in Florida case law that has figuratively “killed” unlicensed contractors. Here’s another one. The moral to this trend and case is simple: make sure you have the proper licenses prior to serving as a contractor under Florida law. Trying to be cute, as seemed to be the situation in this case with a creative argument, is not an argument that will carry the day and your resources will be devoted to being creative versus the ultimate merits of the dispute.
In Ramindesign, LLC v. Skarzynski, 2026 WL 1649571 (S.D.Fla. 2026) an owner of real property hired a company to design and construct a spec home on the property. The company and its owner were NOT licensed contractors. The contract stated the company was serving as a “spec developer” and referred to it as the contractor throughout the contract. Other than this, the contract was set up as a cost plus a fee.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
A Permitting Base Checklist for Data Centers and Power Plants
June 02, 2026 —
Michael S. McDonough, Stephen J. Humes & Stacey C. Wright - Gravel2Gavel Construction & Real Estate Law BlogThere is a lot of talk these days about “license to operate” for data centers, meaning management of the relationships with stakeholders and broader communities concerning both the benefits and adverse consequences of locating a facility in a particular locale. Here, we are speaking of “license to operate” more literally—namely, the legal and regulatory permitting and approval requirements for a privately owned data center whether by itself or colocated with a power generating plant.
Our Base Checklist includes generally and potentially applicable permitting requirements for development and operation, using California as an example. (Taking legal authority Frank Sinatra out of context, “If you can make it there, you can make it anywhere.”) The actual requirements for a given facility would depend, in part, on local law, including planning and zoning laws and plans, and the environment of the site. Just as examples, additional permitting and mitigation requirements might apply if sensitive receptors are located nearby (e.g., noise mitigation for residential dwellings), if sensitive and protected biological resources (e.g., jurisdictional waters and/or protected species) would be impacted, or if the present or former land uses require additional measures (e.g., hazardous materials remediation, mitigation for conversion of prime farmland, or protection of cultural resources). The scope of permit requirements would ultimately be determined by the applicable regulatory agencies and by the lead and responsible agencies under the applicable state environmental land use regime—in our reference case here, the California Environmental Quality Act (CEQA).
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Stephen J. Humes, Pillsbury and
Stacey C. Wright, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. Wright may be contacted at stephen.humes@pillsburylaw.com
Read the full story...
Court Compels Appraisal Although Coverage Issues Exist
February 17, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe California federal district court granted the insured’s motion to compel appraisal despite the existence of outstanding coverage issues. K4 Dev. LLC v. ACE Am. Ins. Co., et al., 2025 U.S. Dist. LEXIS 211337 (C.D. Cal. Oct. 6. 2025).
The insured owned hotel property. It was insured by ACE while the hotel was under construction. During construction, the hotel suffered rainwater damage due to incomplete roofing systems. The water damaged the interior finishes and furnishings from the 6th floor down to the basement, including 32 guestrooms.
The insured’s experts determined that the covered water losses delayed the hotel’s opening by 144 days. The insured submitted a claim for the water damage, covered claim expenses, and delay in opening losses. ACE denied the claim for delay in opening losses, stating that its expert determined the Water Events did not delay the hotel’s opening. ACE, however, did pay for the repair damage caused by the Water Events.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contractor Dispute Resolution Framework and Prevention
July 06, 2026 —
Construction ExecutiveWHAT DEFINES A CONTRACTOR DISPUTE RESOLUTION FRAMEWORK
A contractor dispute resolution framework is a structured system of contractual terms, governance processes and escalation pathways designed to prevent, manage and resolve conflicts between contracting parties with minimal disruption to cost, schedule and performance.
The framework operates as both a preventive control and a corrective mechanism. Preventive elements establish clarity in scope, expectations and accountability before work begins. Corrective elements define how disagreements are identified, documented, escalated and resolved once they arise.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
SDNY Ruling Highlights Privilege Risks in Client Use of Generative AI
March 03, 2026 —
Christopher J. Olsen, Freddy X. Muñoz & Gary M. Stein - Peckar & Abramson, P.C.Artificial intelligence is quickly becoming a go‑to tool for aggregating and summarizing large volumes of data, formulating and testing arguments, and even sketching litigation strategies. But a recent ruling from the Southern District of New York serves as a stark warning: when clients turn to generative AI for legal strategy, they may be unknowingly turning privileged information over to a third party and then creating documents that may later be discoverable in litigation. In a closely watched bench decision, Judge Rakoff ruled that AI‑generated documents created by the target of a criminal investigation using Anthropic’s Claude were not privileged despite being generated with information learned from his attorneys to support his potential legal defense and then shared with his counsel. The decision highlights the unresolved and increasingly consequential intersection of AI, privilege, and discovery.
Facts
Bradley Heppner received a grand jury subpoena and hired attorneys at Quinn Emanuel to represent him. After learning he was a target of the investigation, but before he was arrested, he created 31 documents with Claude using information from his attorneys to outline a potential defense strategy. He was later arrested on charges of securities and wire fraud, and federal agents seized his electronic devices, which contained the 31 documents that had been provided to his attorneys. Mr. Heppner argued that the documents were created to prepare his potential defense strategy in anticipation of an indictment, but he conceded that he made the decision to prepare the reports on his own, i.e., not at the direction of counsel. He nevertheless claimed the documents were protected from disclosure by the attorney-client privilege and work product doctrine; the government moved to overrule the objections.
Reprinted courtesy of
Christopher J. Olsen, Peckar & Abramson, P.C.,
Freddy X. Muñoz, Peckar & Abramson, P.C. and
Gary M. Stein, Peckar & Abramson, P.C.
Mr. Olsen may be contacted at colsen@pecklaw.com
Mr. Muñoz may be contacted at fmunoz@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Read the full story...